文章目录

  • 一、Tracking progress
    • 1.What is a project schedule, an activity, and a milestone
    • 2.Work breakdown and activity graphs
    • 3.Estimating completion
      • (1)CPM (Critical Path Method) (*)
      • (2)Slack time for an activity
    • 4.Tools to track progress
  • 二、Project personnel
    • 1.Staff roles and characteristics
      • (1)Communication
    • 2.Work styles
    • 3.Project organization
      • (1)Depend on three factors
      • (2)Chief programmer team
      • (3)Egoless approach无私方法
  • 三、Effort estimation
  • 四、Risk management activities
    • 1.What is a risk?
    • 2.Steps in risk management
      • Risk exposure calculation
    • 3.How to reduce risk?

一、Tracking progress

1.What is a project schedule, an activity, and a milestone

2.Work breakdown and activity graphs

4 parameters to describe an activity: precursor, duration, due date, and endpoint
Activity graph

3.Estimating completion

(1)CPM (Critical Path Method) (*)

(2)Slack time for an activity

都以Activity(前者-后者)的前者为基准。

  • Critical path关键路线 :
    从开始到结束得所有路径中,所用时间最长的为关键路径(有可能有多条相同的)。

  • 最早开始时间(以前者为基准):
    在关键路径上,从开始到该任务的最早执行的时间
    第一个结点(开始结点)的最早执行的时间是1,不是0.
    其他结点的最早开始时间为:[从开始结点到Activity前者结点经过的最长的时间总长]+1

  • 最晚开始时间(以前者为基准):
    关键路径的总时间-反向得出该任务的时间
    关键路径上的Activity(前者、后者都在)的最晚开始时间是同最早开始时间。
    其他结点的最晚开始时间为:关键路线的总时长 - [从结束结点到Activity前者结点经过的最长的时间总长]+1

  • Slack time松弛时间:
    第一种求法:最晚开始时间-最早开始时间
    第二种求法:关键路径的总时间-包含该任务的关键路径花的时间
    关键路径上的Activity(前者、后者都在)的Slack time为0.

  • Precursors前驱结点:
    是Activity(前者-后者)中前者的前驱结点。

【应用题1】


比如:
2-3的最早开始时间为3+1=4,最晚开始时间为=15-(2+2+3)+1=9
2-4的最早开始时间为3+1=4,最晚开始时间为=15-(5+2+3)+1=6
3-7的最早开始时间为2+3+1=6,最晚开始时间为=15-(2+3)+1=11
5-7的最早开始时间为3+3+1=7,最晚开始时间为=15-(3+6)+1=7

【应用题2】


F-H的最早时间和C-F、D-F的最晚时间中的经过时间都是取得经过的最长时间

4.Tools to track progress

Gantt chart

二、Project personnel

1.Staff roles and characteristics

(1)Communication

If there is n worker in project, then there are n(n-1)/2 pairs of communication.

【选择题】

  • There are ( 15 )communications paths in a team with 6 members.

2.Work styles

  • Extroverts(外向): tell their thoughts
  • Introverts(内向): ask for suggestions
  • Intuitives(直觉): base decisions on feelings
  • Rationals(理智): base decisions on facts, options
    【选择题】
  • Shane is an efficient leader(外向的).He knows what he wants and relies on his own experiences and logic to make decisions.(依据逻辑)He does not feel the need for extensive information before making a decision.He is capable of making fast decisions.Shane’s work style would be described best as ( Rational extrover

3.Project organization

(1)Depend on three factors

  • backgrounds and work styles of team members
  • number of people on team
  • management styles of customers and developers

(2)Chief programmer team

【选择题】

  • A chief programmer team is not suited for ( adopting a new programming language )projects.

(3)Egoless approach无私方法

题:
【选择题】

  • An egoless approach is suited for adopting a new programming language.(采取新的编程语言)

三、Effort estimation

Can not produce accurate estimates
Effort estimation techniques – expert judgment, algorithmic methods, machine-learning ethods

四、Risk management activities

1.What is a risk?

2.Steps in risk management


分为Risk assessment风险评估和Risk control风险控制:

  • Risk assessment风险评估:

    • Risk identification风险定义
    • Risk analysis风险分析
    • Risk prioritization风险优先次序
  • Risk control风险控制:
    • Risk reduction风险减少
    • Risk management planning风险管理计划
    • Risk resolution风险解决
      【选择题】
  • Risk management planning)is not an activity of risk assessment.

Risk exposure calculation

Risk exposure(成本) = (risk probability) x (risk impact)
【应用题1】




【应用题2】



3.How to reduce risk?

三:Planning and Managing the Project相关推荐

  1. PMI-PMP®远程模考三 正题数

    单选题 (每题1分,共168道题) 1. [单选] 一个项目连续错过交付日期,项目团队评估完该情况后,项目经理意识到团队绩效差的原因在于团队成员对于自己的职责缺乏清晰认识.项目经理首先应该关注哪一项? ...

  2. 2020PMP(第六版)每日三题

    PMP12月份考试已经顺利通过,这里将平时积累的每日三题发出来供大家分享:(结尾分享一点考试心得体会) 一.题目部分: 2020.9.27 三题: 1.项目是: A. 一组持续的活动中执行的一个过程或 ...

  3. 软件项目管理考点整理(Software Project Management)

    前言 由于是全英文考试,以下笔记是中英文混合~~ 一.Project Management Overview (1) project定义: A project is a temporary endea ...

  4. PMP备考错题集-模拟三

    1.一家组织正在开展一个软件应用程序开发项目,有不同的相关方参与到该项目的不同阶段.项目经理应该如何让相关方在整个项目过程中参与? An organization is working on a so ...

  5. PMP新考纲 敏捷题目 (三)

    61.传统管理的项目使用Scrum来开发项目可交付成果.敏捷发布规划要求将最近完成的MVP部署到生产中.然而,质量保证(QA)部门拒绝了MVP,声称部门的政策和程序没有处理中期可交付成果的实施.将问题 ...

  6. System Analysis and Project Management

    Lecture 1 What is a project? What is the difference between project, job and exploration? What is an ...

  7. Real Web Project Management: Case Studies and Best Practices from the Trenches

    版权声明:原创作品,允许转载,转载时请务必以超链接形式标明文章原始出版.作者信息和本声明.否则将追究法律责任. http://blog.csdn.net/topmvp - topmvp The pro ...

  8. 2.3 CMMI2级——项目跟踪和控制(Project Monitoring and Control)

    计划不是用来看的,是用来执行的.PP讲述了如何做计划,PMC讲述的就是如何跟踪计划的执行并在实际情况偏离计划时采取纠正行动. 我们先看看SG1,SG1讲述的是如何根据计划来跟踪计划的执行问题. SG1 ...

  9. .NET Core系列 : 2 、project.json 这葫芦里卖的什么药

    .NET Core系列 : 1..NET Core 环境搭建和命令行CLI入门 介绍了.NET Core环境,本文介绍.NET Core中最重要的一个配置文件project.json的相关内容.我们可 ...

最新文章

  1. TFS发布计划发送到钉钉消息群
  2. Oracle中常用的命令,随着学习进度总结
  3. Android 插件化原理解析——插件加载机制
  4. Spring Cloud Eureka 配置原理详解
  5. 刷前端面经笔记(九)
  6. gradle mysql依赖关系,如何在gradle中找到\删除未使用的依赖关系
  7. 无人机可能又闯祸了:这次导致美国一架直升机坠毁
  8. 关于mysql数据库的说法错误的是_MYSQL数据库2013-2014学年考试试卷
  9. php里= 啥意思,PHP natcasesort() 函数 | 菜鸟教程
  10. 极域电子书包课堂管理系统_朝阳群众说小康 | 从黑板课本到VR互动课堂、电子书包,朝阳的课堂如此有趣!...
  11. MATLAB高斯平顶化,一种高斯光束变换为平顶光束整形透镜的粒子群设计方法与流程...
  12. 美术集网校—多点透视如何运用于绘画中?学会透视增加绘画体积感!
  13. MMORPG端游《ELYON》12月10日上线 采用买断式收费方式
  14. Java用POI导出Excel合并单元格、字体、居中样式
  15. CAD三维图自动生成三视图
  16. 服务器系统如何合理分区,裸金属服务器操作系统分区建议
  17. jmeter伪造ip进行压测(伪造大量ip,测试负载均衡)
  18. Java 面向对象(六)
  19. ubuntu安装更新命令
  20. PS海绵工具加深工具简单工具的区别

热门文章

  1. 虚拟机服务器开启也显示内部错误,VMware Workstation开启虚拟机时提示“内部错误”的原因及解决方法...
  2. 至高之战服务器位置在哪里,至高之战专业系统
  3. Jetpack Paging 思想在起点读书的最佳实践 | 开发者说·DTalk
  4. 她坐在奔驰车盖上哭泣,她的手机号还被泄露
  5. c语言经典100例c20 比赛顺序
  6. 机械妖姬上门要源码,给她吗?
  7. linux命令行网络带宽检测工具
  8. 使用css属性,使div上下左右移动
  9. 公司开发网站怎么对接短信平台?
  10. php播放器隐藏播放地址,window_ASP中实现对MediaPlayer控件播放文件地址隐藏的解决方案,在播放视频时,直接查看页面 - phpStudy...