从进入CDC, 整个研发团队是瀑布开发模式, 瀑布模型(Waterfall Model)瀑布模型是将软件生存周期的各项活动规定为按固定顺序而连接的若干阶段工作,形如瀑布流水,最终得到软件产品。

说到这里,首先要定义角色

ROLES AND RESPONSIBILITIES

  • PJM(项目管理者)

    • supervise schedule for work ordered to other teams (督导时间表,安排好与其他团队的工作)
    • risk and cost management (风险管理和费用(成本)管理)
    • driving overall project progress for each stage(驱动在每一个阶段的项目进度 )
    • cross-team process creation, update and discussions (跨团队的任务的创建、更新和讨论)
    • inform DVM about quality concerns (提示DVM关注项目质量)
    • manage project management tools (管理项目管理工具,例如Jira,confluence)
  • DVM (开发管理者)

    • enforce process (实施进程)
    • drive timely delivery of high-quality code (驱动及时交付高质量的代码)
    • provide estimates in order to know what to include in each release as well as to calculate ROI (提供每个发布包含哪些内容的预估并且计算ROI)
    • Engage PJM to deal with outside Ichiba team schedule, risk and issues as soon as possible. (DVM及时发现开发中的问题,并及时跟PJM沟通,以确保PJM能够尽快地处理与外部团队的排期,风险和问题)
  • PDM (产品管理者)

    • enforce process(实施进程)
    • set priority for features, and bugs when needed (设定产品特征和BUG的优先级)
    • drive delivery of high-quality specifications (驱动交付高质量的式样)
    • regularly inform team members about product roadmap (定期向团队成员公布产品路线图)
    • provide GMS estimates in order to prioritize requirements as well as to calculate ROI (提供GMS来排定需求的优先级)
    • create user manuals and release notes (创建用户手册和发布说明)
    • Engage PJM to deal with outside Ichiba team schedule, risk and issues as soon as possible. (PDM及时发现式样定义中的问题,并及时跟PJM沟通,以确保PJM能够尽快地处理与外部团队的排期,风险和问题)
    • test releases, ensure high quality (测试发布的版本,确保高质量输出)
Process Time Responsibilities Role Participants

Deliverable

comment
0. Management
  Budget Management PJM Cost Model
  Time Management (overall) PJM Excel Schedule and WBS
  Time Management (detailed)
  • Requirements: PDM (assisted by PJM)
  • Development work: DVM (assisted by PJM)
PJM receives estimations for Due Dates and input into Project schedule
  Coordination with CWD (detailed) PDM
  Coordination with BU PDM PJM PDM: 分享季度开发计划
1. Prepare Budget Application

1st week at month of prepare budget application

(case by case)

Preliminary requirements discussion
(初步需求讨论会)

PDM

Team Leader
Minrong

Shiwei(Option)
SSP(Option)

  1. 讲解案件初步需求,讨论、确定涉及的服务
  2. 评估技术的可行性;
  3. 起案的合理性;
  4. 预估案件大小(工数),
  5. 是否需要分期及技术角度的分期建议
  6. 确认是否有其他开发团队参与

7. 确定PJM

  2nd week at month of prepare budget application Functional Specification (detailed) PDM Team Leader
PJM

Confluence document
确定DVM

3rd week at month of prepare budget application

(case by case)

prototype design discussion
(原型讨论会)
PDM

Team Leader
PJM
DVM 
ENG

1.工数的预估(给出哪些无法预估)
2.评估所需资源(infra、CWD等)
1.讲解需求UI的呈现及交互方式,讨论、确定交互及UI呈现的可行性、合理性
 

4th week at month of prepare budget application

(case by case)

Draft MRD

(初稿MRD讨论会)

PDM PJM
DVM
ENG
The modifying part of draft MRD 讲解MRD(MRD PPT初稿),讨论、确定MRD中描述的需求及范围的准确性、合理性;

4th week at month of prepare budget application

(case by case)

MRD fixed PDM PJM
DVM
ENG
Fixed MRD

讲解fixed MRD,最终确认MRD;

2. 确认有其他开发团队参与,则需准备相应的英文资料,并约相关团队进行MRD的讲解。

2.Budget Application

1-Budget Application
 

Month of budget application

Send MRD (English version) to CWD PDM Notice the month of budget application , to remain the resource.
 

1st weeks at month of budget application

Estimate Development Effort DVM ENG Submit human cost and schedule to DVM
1st weeks at month of budget application Adjusting human resource DVM Submit human cost and schedule to PJM
1st weeks at month of budget application Meeting with Infra member for infra Estimate

PJM

DVM

ENG

Meeting minutes from discussions with Infra Members (PDM introduce project, DVM Submit apply content)
  1st weeks at month of budget application QA Estimate PJM PDM

Supply budget to Admin for update of ROS.

  1st weeks at month of budget application Security Audit Estimate PJM System Security Office

Supply budget to Admin for update of ROS.

  1st weeks at month of budget application Create Overall Schedule PJM

DVM

PDM

Excel Schedule
  1st weeks at month of budget application Create Detailed Schedule (implementation) DVM Detailed Schedule
2nd weeks at month of budget application

Explain of Schedule and Mandays

PJM DVM Approved Schedule and Mandays

DVM to report Mandays

PJM to report Schedule

  Approved on Friday of 2nd weeks at month of budget application

Business Case Creation and Approval

PDM/PJM

Project introduction PPT

Mandays, Schedule, BudgetApplication,

Taiwan Service Decision Making MTG summit and get approval

PDM : Project introduction PPT (Function, KPI)

PJM: BudgetApplication,Mandays, Schedule)

2nd weeks at month of budget application PMO Ticket PJM Submit PMO ticket to SSP get approval
3rd weeks at month of budget application

Registration in EYES

PJM

Send Email to Japan PDM to support get EYES Code in EYES system.

3rd weeks at month of budget application Dezi Ticket PJM Submit DEZI ticket to apply budget
3. Project Start Phase 0_Project Start
 

1st week

before design stage

Process Design (development process. select tools) PJM

Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Communication Management PJM Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Project Objectives PJM Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Education (project management training) PJM

reference:

0_Project Start

1-3 days before design stage

Project start Meeting PJM DVM,PDM,ENG All project members to attend (about MRD question, Schedule .etc)
1-3 days before design stage Create WBS PJM WBS Milestone (Task of each stage)
1-3 days before design stage Create Detailed WBS DVM WBS (Design, development,ENG test,Release) detailed task
1-3 days before design stage Create Detailed WBS PDM WBS (PM test) detailed task

1st week

before design stage

UI Specification Meeting PDM CWD UI Specification document
case by case UI Design Estimate according to UI Specification CWD Estimated man-days and cost PDM need to confirm with Taiwan
case by case Provide the Due date according to ENG' schedule PDM Due date for providing HTML
case by case Provide CWD Schedule according to ENG's due date CWD CWD Schedule
4. Design and design review
Design 3-5 Days Overall Architecture DVM ENG Confluence documentation
DB Schema Design DVM ENG Confluence documentation
Hardware Design DVM ENG Apply to Infra and Confluence documentation
Application Design (RMS/MALL) DVM ENG Confluence documentation
Design Review 1-2 Days Overall Architecture Team Manager : ZhuShiwei DVM Approved documentation Architecture Design and Program Design
DB Schema Design Team Leader DVM,ENG Approved documentation
Hardware Design Infra Members DVM,ENG Approved documentation
Application Design (RMS/MALL) Team Leader DVM,ENG Approved documentation
Case by case Create Mock-ups CWD PDM
Case by case Confirm Mock-ups PDM Confirmed Mock-ups PDM need to confirm with Taiwan
Case by case Create Design (Image Description) CWD PDM
Case by case Confirm Design (Image Description) PDM Confirmed Design (Image Description) PDM need to confirm with Taiwan
Case by case Create HTML page CWD PDM
case by case

Confirmed HTML page

DVM/PDM ENG Confirmed HTML source file (确定设计原型) PDM need to confirm with Taiwan
Apply support ASAP Apply QA  PJM Apply JIRA ticket to QA
ASAP Apply Appscan DVM Apply JIRA ticket to System Security Office
ASAP Apply Security Audit DVM Apply JIRA ticket to System Security Office
The last day of design stage Design finished MTG (CDC) DVM

ENG

PJM

PDM(Option)

Confluence documentation(Architecture Design Document,Program Design Dcoument)

 All project members to attend (Judge to whether can enter the next phase )
5.Development & Unit test  3-Development
Case by case Programing DVM ENG Coding
Case by case Unit Test DVM ENG

(Unit Test Code Coverrage(>=80%)

3-5 days Code Review DVM ENG Code source
6.DEV Test
Prepare test case DVM ENG Test case document
DEV Release DVM ENG n/a
Dev Test DVM ENG Problem tickets
Bug Fix after Test DVM ENG Fixed ticket
1-2 days before dev test finished DEV test result Demo MTG DVM

ENG

PJM

PDM(Option)

Demonstrable function

ENG demonstrate their own development efforts on DEV
7.Internal STG Test  4-Internal STG Test
2-5 days  Prepare Join Test Case PDM Created test cases
1 day Test case review MTG PDM

DVM

ENG

PJM(Option)

Meeting with DVM, and review the test case
1 week or more Prepare Load Test Case DVM ENG DVM arraign Eng prepare Load test case document
1 days Load test case review DVM review Load test case
5 days

INFRA (JP) Review Load test case

DVM Need to INFRA (JP) Review Load test case
case by case Join Test (ENG) DVM ENG DVM arraign Join Test by ENG 
1-2 days before Eng stg test finished STG test result Demo MTG DVM

ENG

PJM

PDM

ENG demonstrate their own development efforts on STG, PDM attend.
case by case Join Test (PDM) PDM ENG Join Test Report STG测试结束以后发出report说明STG阶段结束
3-5 days Load Test DVM ENG

Load Test report

DVM arraign Eng to do Load Test, and submit Load Test report to INFRA (JP)
8.External STG Test  5-External STG Test
1 weeks before QA test QA Test case review PDM/DVM

QA test case docuement

PDM review UI part,
DVM review function part and flow part.
case by case QA Test QA Team

PDM

DVM

Problem tickets
3-5 days QA Test after bugfix DVM ENG Fixed ticket DVM arraign arraign to fix these tickets
1-3 days Appscan Test

Executed by CDC (DVM)

Executed by SSO

Appscan Test report
0 or 1 day Appscan Test after bugfix DVM ENG Fixed ticket DVM arraign arraign to fix these tickets
3 ~5 days Security Audit Test Executed by SSO Security Audit Test report
0 or 2 days Audit Test after bugfix DVM ENG Fixed ticket DVM arraign ENG to fix these tickets
case by case JV Test JV PDM/Eng Fixed ticket DVM arraign ENG to fix these tickets
9.Release Release

Reference: Service Operation

[Service Transit] Release & Service Test Work Flow

1-2 weeks before release Merge code and Tag and test DVM ENG

Merged code

2 weeks before release Prepare TimeSchedule and release manual DVM ENG

TimeSchedule

Operation manual

2 weeks before release Prepare Release confirm manual PDM Confirm manual
2 weeks before release Release manual Review DVM reviewed Release manual
2 weeks before release TimeSchedule Review meeting DVM

PDM

ENG

PJM

TimeSchedule Share TimeSchedule to all please release members
2 weeks before release Release Rehearsal DVM/PDM ENG Confirmed TimeSchedule/Operation manual/Confirm manual Release Rehearsal on STG
2 weeks before release Adjuest after Release Rehearsal DVM ENG Fixed function or UI Adjuest after Release Rehearsal on STG
1-2 weeks before release Release Plan Sharing on IIPM(Option) PDM IIPM Report Share Release Plan
1 week before release Release Judge meeting PJM

DVM

PDM

TM (Shiwei)

SSP(Fumiyama)

Judgment Sheet

PJM will report the whole progress

DVM will report the detail (Such as load test , time schedule)

1-3 days before release

Release Announcement

(Option)

PJM Announcement JIRA ticket

Taiwan Service Decision Making MTG summit

(Stop Maintenance or affect on taiwan services need to share)

1-2 days Release DVM PJM/PDM

New function on Pro

PJM to send srart and finished email ,and to lead the release.

DVM to do release operation according to operation manual

PDM to do confirm operation according to confirm manual

10.Retrospect
1 week after project release

Retrospective Meeting

PJM

DVM

PDM

ENG

TL

Meeting minutes of retrospective Meeting  All project members to attend
2nd months after project release KPI Monitoring(Option) PDM IIPM report
11.Post-deploy Phase
  Troubleshooting PDM/ENG
Process Time Responsibilities Role Participants

Deliverable

comment
0. Management
  Budget Management PJM Cost Model
  Time Management (overall) PJM Excel Schedule and WBS
  Time Management (detailed)
  • Requirements: PDM (assisted by PJM)
  • Development work: DVM (assisted by PJM)
PJM receives estimations for Due Dates and input into Project schedule
  Coordination with CWD (detailed) PDM
  Coordination with BU PDM PJM PDM: 分享季度开发计划
1. Prepare Budget Application

1st week at month of prepare budget application

(case by case)

Preliminary requirements discussion
(初步需求讨论会)

PDM

Team Leader
Minrong

Shiwei(Option)
SSP(Option)

  1. 讲解案件初步需求,讨论、确定涉及的服务
  2. 评估技术的可行性;
  3. 起案的合理性;
  4. 预估案件大小(工数),
  5. 是否需要分期及技术角度的分期建议
  6. 确认是否有其他开发团队参与

7. 确定PJM

  2nd week at month of prepare budget application Functional Specification (detailed) PDM Team Leader
PJM

Confluence document
确定DVM

3rd week at month of prepare budget application

(case by case)

prototype design discussion
(原型讨论会)
PDM

Team Leader
PJM
DVM 
ENG

1.工数的预估(给出哪些无法预估)
2.评估所需资源(infra、CWD等)
1.讲解需求UI的呈现及交互方式,讨论、确定交互及UI呈现的可行性、合理性
 

4th week at month of prepare budget application

(case by case)

Draft MRD

(初稿MRD讨论会)

PDM PJM
DVM
ENG
The modifying part of draft MRD 讲解MRD(MRD PPT初稿),讨论、确定MRD中描述的需求及范围的准确性、合理性;

4th week at month of prepare budget application

(case by case)

MRD fixed PDM PJM
DVM
ENG
Fixed MRD

讲解fixed MRD,最终确认MRD;

2. 确认有其他开发团队参与,则需准备相应的英文资料,并约相关团队进行MRD的讲解。

2.Budget Application

1-Budget Application
 

Month of budget application

Send MRD (English version) to CWD PDM Notice the month of budget application , to remain the resource.
 

1st weeks at month of budget application

Estimate Development Effort DVM ENG Submit human cost and schedule to DVM
1st weeks at month of budget application Adjusting human resource DVM Submit human cost and schedule to PJM
1st weeks at month of budget application Meeting with Infra member for infra Estimate

PJM

DVM

ENG

Meeting minutes from discussions with Infra Members (PDM introduce project, DVM Submit apply content)
  1st weeks at month of budget application QA Estimate PJM PDM

Supply budget to Admin for update of ROS.

  1st weeks at month of budget application Security Audit Estimate PJM System Security Office

Supply budget to Admin for update of ROS.

  1st weeks at month of budget application Create Overall Schedule PJM

DVM

PDM

Excel Schedule
  1st weeks at month of budget application Create Detailed Schedule (implementation) DVM Detailed Schedule
2nd weeks at month of budget application

Explain of Schedule and Mandays

PJM DVM Approved Schedule and Mandays

DVM to report Mandays

PJM to report Schedule

  Approved on Friday of 2nd weeks at month of budget application

Business Case Creation and Approval

PDM/PJM

Project introduction PPT

Mandays, Schedule, BudgetApplication,

Taiwan Service Decision Making MTG summit and get approval

PDM : Project introduction PPT (Function, KPI)

PJM: BudgetApplication,Mandays, Schedule)

2nd weeks at month of budget application PMO Ticket PJM Submit PMO ticket to SSP get approval
3rd weeks at month of budget application

Registration in EYES

PJM

Send Email to Japan PDM to support get EYES Code in EYES system.

3rd weeks at month of budget application Dezi Ticket PJM Submit DEZI ticket to apply budget
3. Project Start Phase 0_Project Start
 

1st week

before design stage

Process Design (development process. select tools) PJM

Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Communication Management PJM Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Project Objectives PJM Confluence documentation

reference:

0_Project Start

 

1st week

before design stage

Education (project management training) PJM

reference:

0_Project Start

1-3 days before design stage

Project start Meeting PJM DVM,PDM,ENG All project members to attend (about MRD question, Schedule .etc)
1-3 days before design stage Create WBS PJM WBS Milestone (Task of each stage)
1-3 days before design stage Create Detailed WBS DVM WBS (Design, development,ENG test,Release) detailed task
1-3 days before design stage Create Detailed WBS PDM WBS (PM test) detailed task

1st week

before design stage

UI Specification Meeting PDM CWD UI Specification document
case by case UI Design Estimate according to UI Specification CWD Estimated man-days and cost PDM need to confirm with Taiwan
case by case Provide the Due date according to ENG' schedule PDM Due date for providing HTML
case by case Provide CWD Schedule according to ENG's due date CWD CWD Schedule
4. Design and design review
Design 3-5 Days Overall Architecture DVM ENG Confluence documentation
DB Schema Design DVM ENG Confluence documentation
Hardware Design DVM ENG Apply to Infra and Confluence documentation
Application Design (RMS/MALL) DVM ENG Confluence documentation
Design Review 1-2 Days Overall Architecture Team Manager : ZhuShiwei DVM Approved documentation Architecture Design and Program Design
DB Schema Design Team Leader DVM,ENG Approved documentation
Hardware Design Infra Members DVM,ENG Approved documentation
Application Design (RMS/MALL) Team Leader DVM,ENG Approved documentation
Case by case Create Mock-ups CWD PDM
Case by case Confirm Mock-ups PDM Confirmed Mock-ups PDM need to confirm with Taiwan
Case by case Create Design (Image Description) CWD PDM
Case by case Confirm Design (Image Description) PDM Confirmed Design (Image Description) PDM need to confirm with Taiwan
Case by case Create HTML page CWD PDM
case by case

Confirmed HTML page

DVM/PDM ENG Confirmed HTML source file (确定设计原型) PDM need to confirm with Taiwan
Apply support ASAP Apply QA  PJM Apply JIRA ticket to QA
ASAP Apply Appscan DVM Apply JIRA ticket to System Security Office
ASAP Apply Security Audit DVM Apply JIRA ticket to System Security Office
The last day of design stage Design finished MTG (CDC) DVM

ENG

PJM

PDM(Option)

Confluence documentation(Architecture Design Document,Program Design Dcoument)

 All project members to attend (Judge to whether can enter the next phase )
5.Development & Unit test  3-Development
Case by case Programing DVM ENG Coding
Case by case Unit Test DVM ENG

(Unit Test Code Coverrage(>=80%)

3-5 days Code Review DVM ENG Code source
6.DEV Test
Prepare test case DVM ENG Test case document
DEV Release DVM ENG n/a
Dev Test DVM ENG Problem tickets
Bug Fix after Test DVM ENG Fixed ticket
1-2 days before dev test finished DEV test result Demo MTG DVM

ENG

PJM

PDM(Option)

Demonstrable function

ENG demonstrate their own development efforts on DEV
7.Internal STG Test  4-Internal STG Test
2-5 days  Prepare Join Test Case PDM Created test cases
1 day Test case review MTG PDM

DVM

ENG

PJM(Option)

Meeting with DVM, and review the test case
1 week or more Prepare Load Test Case DVM ENG DVM arraign Eng prepare Load test case document
1 days Load test case review DVM review Load test case
5 days

INFRA (JP) Review Load test case

DVM Need to INFRA (JP) Review Load test case
case by case Join Test (ENG) DVM ENG DVM arraign Join Test by ENG 
1-2 days before Eng stg test finished STG test result Demo MTG DVM

ENG

PJM

PDM

ENG demonstrate their own development efforts on STG, PDM attend.
case by case Join Test (PDM) PDM ENG Join Test Report STG测试结束以后发出report说明STG阶段结束
3-5 days Load Test DVM ENG

Load Test report

DVM arraign Eng to do Load Test, and submit Load Test report to INFRA (JP)
8.External STG Test  5-External STG Test
1 weeks before QA test QA Test case review PDM/DVM

QA test case docuement

PDM review UI part,
DVM review function part and flow part.
case by case QA Test QA Team

PDM

DVM

Problem tickets
3-5 days QA Test after bugfix DVM ENG Fixed ticket DVM arraign arraign to fix these tickets
1-3 days Appscan Test

Executed by CDC (DVM)

Executed by SSO

Appscan Test report
0 or 1 day Appscan Test after bugfix DVM ENG Fixed ticket DVM arraign arraign to fix these tickets
3 ~5 days Security Audit Test Executed by SSO Security Audit Test report
0 or 2 days Audit Test after bugfix DVM ENG Fixed ticket DVM arraign ENG to fix these tickets
case by case JV Test JV PDM/Eng Fixed ticket DVM arraign ENG to fix these tickets
9.Release Release

Reference: Service Operation

[Service Transit] Release & Service Test Work Flow

1-2 weeks before release Merge code and Tag and test DVM ENG

Merged code

2 weeks before release Prepare TimeSchedule and release manual DVM ENG

TimeSchedule

Operation manual

2 weeks before release Prepare Release confirm manual PDM Confirm manual
2 weeks before release Release manual Review DVM reviewed Release manual
2 weeks before release TimeSchedule Review meeting DVM

PDM

ENG

PJM

TimeSchedule Share TimeSchedule to all please release members
2 weeks before release Release Rehearsal DVM/PDM ENG Confirmed TimeSchedule/Operation manual/Confirm manual Release Rehearsal on STG
2 weeks before release Adjuest after Release Rehearsal DVM ENG Fixed function or UI Adjuest after Release Rehearsal on STG
1-2 weeks before release Release Plan Sharing on IIPM(Option) PDM IIPM Report Share Release Plan
1 week before release Release Judge meeting PJM

DVM

PDM

TM (Shiwei)

SSP(Fumiyama)

Judgment Sheet

PJM will report the whole progress

DVM will report the detail (Such as load test , time schedule)

1-3 days before release

Release Announcement

(Option)

PJM Announcement JIRA ticket

Taiwan Service Decision Making MTG summit

(Stop Maintenance or affect on taiwan services need to share)

1-2 days Release DVM PJM/PDM

New function on Pro

PJM to send srart and finished email ,and to lead the release.

DVM to do release operation according to operation manual

PDM to do confirm operation according to confirm manual

10.Retrospect
1 week after project release

Retrospective Meeting

PJM

DVM

PDM

ENG

TL

Meeting minutes of retrospective Meeting  All project members to attend
2nd months after project release KPI Monitoring(Option) PDM IIPM report
11.Post-deploy Phase
  Troubleshooting PDM/ENG  

项目与文档【3001】PJM随谈-基于瀑布开发模型的项目管理相关推荐

  1. Django+Linux+Uwsgi+Nginx项目部署文档

    Django+Linux+Uwsgi+Nginx项目部署文档 WSGI 在生产环境中使用WSGI作为python web的服务器 WSGI:全拼为Python Web服务器网关接口,Python We ...

  2. xxx征集系统项目目标文档

    问题 每四人一组,讨论结束后,每人根据课堂讨论结果提交一份系统利益相关者案例.撰写撰写项目目标文档(目标,好处,度量标准.) 项目目标文档 目标: (1)需求填报 (2)需求查询 (3)需求审核 (4 ...

  3. django+nginx+uwsgi项目部署文档整理

    django+nginx+uwsgi项目部署文档整理 参考文章:https://blog.csdn.net/qq_42314550/article/details/81805328 一.python安 ...

  4. 《重大技术需求征集系统》项目目标文档

    分组:每四人一组 主题:xxx征集系统 成果: 讨论结束后,每组提交一份课堂讨论记录(电子版发表到博客上,纸质版小组成员签名,下节课提交). 每人根据课堂讨论结果提交一份系统利益相关者描述案例.撰写项 ...

  5. 2021-09-10 转载: 软件开发类项目关键文档

    软件开发计划 需求规格说明书 软件概要设计说明 数据库设计说明 软件详细设计说明 可执行程序生成说明 软件测试计划 软件测试说明 软件测试报告 安装部署手册 源代码交付说明 上线部署方案 上线部署实施 ...

  6. 开发人员,请不要抱怨项目没有文档

    每当我们切入一个新项目时,我们发现项目中的文档总是少的可怜,而且里面的设计与当前的系统设计严重不符,有些甚至在架构上出现了严重的偏离.于是我们问待交接人,为什么项目中只有这么点文档,而且文档的内容也不 ...

  7. OpenCV实践小项目(二) -文档ocr扫描识别

    1. 写在前面 今天整理OpenCV入门的第二个实战小项目, 前一篇文章是信用卡数字识别, 主要运用了OpenCV基础图像处理操作里面的轮廓检测, 边缘检测,形态学操作, 今天的这个项目叫做文档ocr ...

  8. postman项目接口文档和登录步骤原理

    培训内容 实训项目:非常果岭-发现模块接口测试,单接口.流程脚本编写: 使用工具:postman 培训方式 1)postman使用说明 2)项目接口文档和登录步骤原理 一.首先了解postman使用 ...

  9. [团队项目]用户需求文档发布!

    用Github浏览更好:Phylab-Web项目用户需求文档 团队主页链接:http://www.cnblogs.com/buaase 用户需求分析文档 版本号:v1.0.2 修订历史: 版本号 修改 ...

最新文章

  1. 68页PPT,读懂中、美、德三国智能制造战略!
  2. 传染病控制(洛谷 1041 WA 90)
  3. 417 Pacific Atlantic Water Flow 太平洋大西洋水流
  4. 184使用 Core Image 框架处理照片
  5. source insight 支持lua /ruby
  6. 米10设置aac格式_Tipard Total Media Converter for Mac(全媒体格式转换器)
  7. 不规则对话框的又一实现
  8. 前端面试题汇总(JS 基础篇)
  9. 【原创】搭建spark环境中的坑及解决办法
  10. CISA:警惕俄罗斯 “Sandworm” 黑客组织使用的新型恶意软件框架
  11. Unity的状态机设计
  12. ReSharper卸载后Visual Studio的快捷键和智能提示消失
  13. lisp 标注螺纹孔_螺纹的标注方法
  14. Python合并两个有序链表
  15. BEC高级商务英语考试应试技巧指南
  16. python名片管理系统2.0_python名片管理系统代码
  17. 电脑c盘满了变成红色了怎么清理?看看这7个方法
  18. 新能源行业商业采购协同系统:赋能新能源行业采购业务,提升产业协同
  19. 中文语音合成综合评测一(可懂度)
  20. ARM基础(5) ARM通讯接口

热门文章

  1. 数据库技术——数据定义与查询
  2. Vue项目如何打包并部署(nginx)
  3. 利用 Ophis 编写 Commodore 64 programs PRG 程序(五)
  4. 学“大神”炒币月收益300%?大神在背后偷偷举起了镰刀……
  5. 怎么测试直播类产品……
  6. java枚举数字_Java枚举类型的使用,数值的二进制表示
  7. 接口自动化系列一: Pytest 夹具统一鉴权, 统一日志输出
  8. Java 刷题11-14
  9. table标签的作用是什么?
  10. 感知自然语言理解(NLU)